How To: Create links between tasks in MS Project 2007

Create links between tasks in MS Project 2007

In this tutorial, we learn how to create links between tasks in MS Project 2007. First, select the task you want to link, then click on the link task button on the toolbar. You will now see a finished task link between these tasks. In the entry table, you will see the predecessor, which is task two. You can also type the numbers in the predecessor column and enter the information in. You may want to create a link that is different, so you don't confuse two things that will start at the same time. When you are finished, make sure to save your project and then you are done!

While you're stuck at home, make the most of your time by learning a new language, skill, or even train for a remote-work job with our new premium online courses.

Check them out >

Our Best Phone Hacks

Gadget Hacks' tips — delivered daily.

Be the First to Comment

Share Your Thoughts

  • Hot
  • Latest