How To: Set up the calendar in MS Project 2007

Set up the calendar in MS Project 2007

In this tutorial, we learn how to set up the calendar in MS Project 2007. First, open up your calendar and then click on the "work week" tab. Now, set your working times into the slots for each different day. Make sure you set your start and end times correctly. Now, go to options and change the default start and end times so they match your working calendar. When finished, save this and then start to enter your task information to each different slot. When you enter this, the start and finish times will then fill themselves in and you can assign different resources to each task. Save when finished!